Rosendin

Maiden, NC

Confidential Data Center

Project Summary

Rosendin provided electrical construction services for this two-phase, build-to-suit data center for an existing technology client. The project includes over 200,000 GSF of prefabricated concrete walls supporting electrical infrastructure comprised of an uninterruptible power supply system supported by diesel generators. The raised data floor components consist of a prefabricated distribution system to accommodate the client’s layout of electronic equipment, as well as an energy-saving hot air, cooling design. In addition to the data infrastructure, this project included over 8,000 SF of Class A office space.

Confidential Data Center

Data Center & Office Space | Prefabricated new construction

Location
Maiden, NC
Client
Confidential
General Contractor
Gilbane Building Company and Turner Construction Company
Duration
25 Months
Budget
$53,488,326
Size
200,000 SF

State Licenses (By Office)

Office License(s)
Anaheim, CA 142881
Gallatin, TN 51692
Hillsboro, OR CCB#103939
Las Vegas, NV 011435
Los Angeles (West), CA 142881
Phoenix, AZ (BIM Office) ROC034937R-11
ROC105241C-11
ROC111444A-17
ROC158637B-1
ROC158638A
Prineville, OR CCB#103939
Sacramento, CA 142881
San Francisco, CA 142881
San Jose, CA (Corp HQ) 142881
Tempe, AZ ROC034937R-11
ROC105241C-11
ROC111444A-17
ROC158637B-1
ROC158638A
Texas TECL20807
B12671901